125-amp subpanel wired in Independence, MO
Independence, MO · Fall 2026
A homeowner in Independence had a new 125-amp subpanel mounted with the feeder and branch circuits pulled in, but nothing connected. One of our pros landed the circuits on new breakers, kept neutrals and grounds on their own bars, labeled the circuits and dressed the wiring. The work cost $200 and took four days from the request to done.
- Job:
- Wire a 125-amp subpanel
- Where:
- Independence, MO
- Done by:
- A FixNeighbor pro
- Cost of the work:
- $200
- Request to done:
- 4 days


What was done
- Check the feeder, the panel rating and the circuits that need to go in.
- Install breakers sized for each circuit's wire.
- Land each circuit: hot on its breaker, neutral on the neutral bar, ground on the ground bar.
- Keep neutrals and grounds separate, as a subpanel requires.
- Label circuits and dress the wiring so the cover goes on cleanly.
Worth knowing about a subpanel
- A subpanel adds breaker space fed from your main panel — common for additions, garages, shops and basements.
- In a subpanel, neutrals and grounds sit on separate bars and are not bonded together. That's one of the first things an inspector looks at.
- Panel work usually needs a permit and inspection. In Independence, check with the city before the cover goes on.
- Turn off power at the main panel before anyone works on a subpanel feeder.
Need something similar?
Describe your job once on FixNeighbor — online or by text to (816) 816-4844 — and add a few photos. Local pros who do this work send you their prices, and you choose. Homeowners pay no service fee.
Questions
- How much does it cost to wire a subpanel?
- This one cost $200 for the work, because the panel was already mounted and the cables were pulled in. Mounting the panel, running the feeder, or upgrading the main panel adds to the price.
- How fast can I get a subpanel connected?
- This job took four days from the request to done. Have the panel, breakers and circuit list ready, and ask about the inspection schedule.
- What should I send to get quotes for subpanel work?
- Photos of the main panel and where the subpanel goes, the panel's amp rating, the circuits you need, and whether the panel and feeder are already in.
More
Electrical in Kansas CityConcrete footing for a new house in Pittsville, MOSix 125-amp services connected at a commercial building in Warrensburg, MONew kitchen countertops with an island in Holden, MONew tiled shower in Pittsville, MOSpray foam insulation in a new home, Lone Jack, MOLow pressure pipe (LPP) septic system installed in Pittsville, MOLarge block retaining wall in Warrensburg, MONew air conditioner installed in Lone Jack, MONew house framing and roof in Pittsville, MONew concrete access driveway in Warrensburg, MOSpray cellulose wall insulation in a new building, Warrensburg, MOKansas City cost guidesHow to get repair quotes